Welding
FAQs
By
Duane K. Miller, Jeff Hietpas, And Rich DePue
Reproduced
with the permission of Welding Journal and the American Welding Society
No matter what branch of the welding
industry you're in, no doubt there are questions that come up time and
time again. The Welding Journal recently asked three active members
of the welding community to provide answers to some of the questions
they are most often asked. The questions and answers from each contributor
follow some short biographical information.
DUANE K.
MILLER, Sc.D., P.E., is manager, Welding Technology Center, and welding
design consultant, The Lincoln Electric Co., Cleveland, Ohio. Miller
is a recognized authority on the design of welded connections. In 1994,
he was selected to chair the American Welding Society's Presidential
Task Group on Northridge earthquake issues. He also served on the Project
Oversight Committee of SAC, a consortium sponsored by the Federal Emergency
Management Agency (FEMA) to provide understanding of connection behavior
in the wake of Northridge. Miller currently serves as first vice chair
of the AWS D1 Committee on Structural Welding and chairs the Seismic
Welding Subcommittee.
Q: What is
undermatched weld metal? Where can I use it? What are the advantages
of undermatched weld metal?
A: When weld
metal strength is compared to the base metal strength, one of three
relationships may exist: the weld metal may be stronger than the base
metal ("overmatched"), generally equivalent to the base metal ("matching"),
or lower than the base metal ("undermatching"). AWS D1.1, Structural
Welding Code -Steel, defines matching and undermatching in the table
in Section 3.3.
In D1.1, overmatching
is never required. Matching strength is required for some connections
and loading types: complete joint penetration (CJP) groove welds in
tension are the most common example. All partial joint penetration (PJP)
groove welds, all fillet welds, and all plug and slot welds can be made
with undermatching weld metal. D1.1 Table 2.3 defines where matching
and undermatching weld metal is required or permitted.
When undermatching
weld metal can be used, the weld is typically more resistant to fabrication-related
cracking. The increased ductility of the lower strength weld metal and
the reduction in residual stresses can reduce lamellar tearing tendencies
as well. Undermatching is typically considered only when the base metal
yield strength is 70 ksi (485 MPa) or greater. A typical application
where undermatching may be considered is when fillet welds are used
to join A514 or A517 steel (minimum specified yield strength of 100
ksi [690 MPa]).
It is important
the weld size reflect the use of undermatching weld metal. Depending
on the particular loads involved, it may be necessary to increase the
specified weld size when undermatching welds, as opposed to matching
strength welds, are used.
Q: We are
a structural steel fabricator. On a recent job, FEMA-353 was specified
in the contract documents. What is FEMA-353 and how will it affect us?
A: FEMA-353,
Recommended Specifications and Quality Assurance Guidelines for Steel
Moment-Frame Construction for Seismic Applications, provides supplemental
design and fabrication recommendations and supplemental quality control
and quality assurance recommendations for the construction of steel
moment frame structures designed for seismic applications. FEMA-353
is designed to supplement other welding codes, such as AWS D1.1, Structural
Welding Code -Steel, or AISC Manual of Steel Construction LRFD.
FEMA 353 contains
provisions that affect welder qualification, filler metals that can
be used, welding procedure specifications (WPSs), inspection practices,
and other issues.
Unfortunately,
there is not enough space here to discuss the numerous recommendations
in FEMA-353. The Lincoln Electric Company has prepared an easy-to-read
brochure, FEMA 353 Welding Manual (C1.60), that summarizes many of the
main welding recommendations in FEMA-353. This manual may be downloaded
or ordered free of charge at www.lincolnelectric.com/products/litre
quest/
Q: Why is
aluminum alloy 7075 not listed in AWS D1.2, Structural Welding Code
- Aluminum?
A: Most aluminum
alloys are weldable, but a fair number of them are not, including 7075
aluminum. When designers and welders look for an aluminum alloy to use,
many will start by reviewing a table that lists all of the aluminum
alloys and their strengths. Alloy 7075 is often selected because it
is one of the highest strength aluminum alloys. But, few of the higher
strength aluminum alloys are weldable, especially those in the 7000
and 2000 series, and they should not be used.
The one exception
to the rule of never using 7075 for welded applications is in the injection
molding industry, which uses 7075 dies and will repair them with welding.
However, 7075 should not be used for structural work.
When you need
to design something of high-strength aluminum, look to a 5000 series
high-magnesium alloy instead of a 2000 or 7000 series. The 5000 series
alloys are weldable and will produce the best results.
Q: Why is
my aluminum welded connection so much weaker than the base material?
A: In steel
weldments, a welded connection can be made as strong as the base material,
but this is typically not the case with aluminum. In almost all instances,
the welded connection will be weaker than the base material.
To understand
why this occurs, consider the two classifications of aluminum alloys:
heat treatable and nonheat treatable. The latter category is hardened
only by cold working, which causes physical changes in the metal. The
more the alloy is cold worked, the stronger it gets. When you weld an
alloy that has been cold worked, you locally anneal the material around
the weld so it goes back to its zero-tempered (or annealed) condition
and it becomes "soft." Therefore, the only time you can make a weld
as strong as the base material with a nonheat-treatable alloy is when
you start with zero-tempered material.
With heat-treatable
aluminum alloys, the last heat treatment step heats the metal to approximately
400°F (200°C). When welding, the material around the weld (the heat-affected
zone) becomes much hotter than 400°F so the material tends to lose some
of its strength. Unless a postweld heat treatment is applied, the area
around the weld will become significantly weaker than the rest of the
aluminum - by as much as 30 to 40%. Post-weld heat treatment can restore
this loss in strength if a heat-treatable aluminum is used.
Table 1 is a
guide as to which series of aluminum alloys are heat treatable and which
are not.
Table 1 - Guide
to Heat-Treatable Aluminum Alloys
Q: Section
12 of AWS D1.5, Bridge Welding Code, addresses fracture control. Shouldn't
this apply to all structures since fracture avoidance is so important?
A: The Engineer
responsible for a product or structure must determine what codes apply
to a project. Further, the Engineer must develop job specifications
that address the specific requirement for specific projects. The Engineer
must also determine whether D1.5 Section 12 is appropriate or not.
The scope and
intent of Section 12 should be understood before it is invoked on a
project. It is intended to apply to "fracture critical members" (FCMs),
which are defined in D1.5, paragraph 12.2.2. It states: "Fracture critical
members or member components are tension members or tension components
of bending members (including those subject to reversal of stress),
the failure of which would be expected to result in collapse of the
bridge." Two elements are important in this definition: tension and
collapse. FCMs must be tension members or tension components. Columns
that see only compressional loading cannot be FCMs.
The collapse
component of this definition has to do with the overall performance
of the bridge should a FCM fracture. Most bridges are redundant, that
is, there are multiple load paths available should a single member fail.
However, a two-girder bridge is likely to be fracture critical in that
the fracture of a single member will likely cause the collapse of the
bridge.
Bridge designers
need to determine whether the bridge member is fracture critical or
not, and specify such on design drawings (see D1.5, paragraph 12.3.1).
For nonbridge applications, the Engineer responsible for the project
needs to determine whether D1.5 Section 12 is applicable. The Engineer
should know it was not the intent of D1.5 to cover nonbridge applications
(see D1.5, paragraph 1.1.1), although it may be appropriate for certain
situations. When applied to nonbridge applications, the Engineer should
realize the materials and product forms (plate, sheet, shapes, tubes)
that will be employed on the nonbridge project may not be covered by
D1.5. Job specifications must address these situations.
Q: New wording
has been added to AWS D1.1, Structural Welding Code - Steel, that addresses
"original equipment manufac- turers" (OEMs). Why was this done and what
does this mean?
A: The section
to which you refer is 1.3.4, which states: "'OEM' shall be defined as
the single Contractor that assumes some or all of the responsibilities
assigned by this code to the Engineer." Historically, D1.1 has outlined
the responsibilities of the parties involved with the typical building
construction process: the Engineer, who acts on behalf of the owner;
the Contractor, the entity that performs the welding; and the various
types of Inspectors. In the typical building construction process, the
Engineer and the Contractor are separate entities. Thus, code responsibilities
assigned to the Engineer are intended to be executed by a different
party than the one doing the fabrication.
Many users of
the D1.1 Code do not fit into this traditional building construction
pattern. For example, the purchaser (owner) of a piece of construction
equipment may require the product be built to D1.1. The manufacturer
of this equipment may have a whole staff of engineers, but in D1.1 terms,
these "engineers" are not the same as the D1.1 "Engineer" who represents
the owner. In this situation, the engineers represent the manufacturer
of the equipment. Thus, application of D1.1 to these situations can
cause a variety of points of confusion.
To address this
situation, the D1 Committee has introduced the OEM concept. The commentary
to D1.1-2002, paragraph 1.3.4, describes this situation in more detail.
Provision 1.4(8) requires contract documents outline the responsibilities
of all the parties involved for OEM applications. The commentary provides
some examples of possible relationships for these applications.
By providing
these new code provisions, it is hoped implementation of D1.1 for applications
other than the typical building construction practice will be simplified.
Q: AWS D
1.3, Structural Welding Code - Sheet Steel, says in its scope that it
covers sheet metal applications "which are equal to or less than 3Ž16
in. (0.188 in./4.8 mm) in nominal thickness" (para. 1.1). AWS D1.1,
Structural Welding Code - Steel, says it is not intended to be used
for applications involving "steels less than 1Ž8 in. (3 mm) thick."
This leaves an overlap between 1Ž8 in. (3 mm) and 3Ž16 in. (4.8 mm)
where (apparently) both codes apply. Which one should I use for applications
where the steel is in this thickness range?
A: The Engineer
responsible for the project must determine which code is applicable.
Applicable codes may be spelled out in contract documents or in building
codes.
The overlap
in thickness between the two codes has several advantages, despite the
confusion created with such overlap. If a project primarily involves
structural steel, and some of those thicknesses drop below 3Ž16 in.
(4.8 mm), D1.1 can be used to address all aspects of the project, providing
no materials are less than 1Ž8 in. (3 mm). Conversely, if a project
involves primarily sheet steel, and some materials are heavier than
1Ž8 in. (3mm), D1.3 can be used to govern all the project, provided
no materials are thicker than 3Ž16 in. (4.8 mm).
One applicable
code on a project has several advantages. Welders need to be qualified
to only one code. Welding Procedure Specifications need only comply
with one code. Inspectors need to refer to only one code. By creating
an overlap in the scope of the two documents, the D1 Committee has eliminated
some of the duplication that would have necessarily resulted if there
were no overlap in coverage.
Consider, for
example, the implications of no overlap. Assume the cut-off point was
1Ž8 in. (3 mm). Assume D1.1 governed 1Ž8 in. and greater, and D1.3 addressed
less than 1Ž8 in. Gauge material of number 10 or thicker (0.1345 in.
[3.416 mm]) would need to be welded to D1.1, but number 11 (0.1196 in.
[3.038 mm]) would be governed by D1.3. Two applicable codes would create
unnecessary confusion. By creating the overlap, the Engineer can select
the most applicable code and, in many situations, one code can be used
to govern all the work being performed.
Jeff Hietpas
has been involved with the welding industry for 29 years. Currently,
he is Product Manager for the Three-Phase Industrial Product Group at
Miller Electric Mfg. Co., Appleton, Wis.
Q: How does
a wire feeder with a four drive roll system affect wire feedability
compared to two drive roll systems?
A: If you're
running your wire feeder on a full-time basis and are using a variety
of wire diameters, it's important to consider a wire feeder with a four
drive roll system. Feeders featuring a two drive roll system have proven
effective, but on anything above 0.045 (and ideally 0.035 and above),
a four drive roll system will assist with a smoother feed. With larger
diameter wires, there is often a great deal of cast that causes stiffening
in the wire. The four drive roll system grips and straightens the wire,
making for an easier feed.
However, in
light fabrication shops where you're set up to run one type of wire
all day and you don't need a lot of flexibility or range in wire (anything
0.035 and below), a two drive roll system will suffice.
Q: What's
being done with wire feeders today to help improve productivity, weld
quality, and overall ease of use?
A: In recent
years, wire feeders have evolved so that they provide a great number
of options that either didn't exist in the past or were not as easy
to use. Some of these options include the following:
- Autodetection
systems are being implemented that can tell if a feeder is hooked
up to a power source with a 14-pin connection for current and voltage
feedback. Newer feeders can now disregard the run-in sequence when
attached to power sources without feedback, eliminating the need to
remove covers and manipulate dip switches, making them ready to use
out of the box, even with older power sources.
- New auxiliary
menus on some machines allow welding supervisors to set locks without
having to toggle dip switches. Locks are protected by codes, making
it nearly impossible for individual operators to toy with settings
and weld at levels not recommended or forbidden on certain applications.
This is a common problem in shops where operators are welding three
shifts a day and you have different welders with different tastes
operating on each machine.
- Today's wire
feeder can be a source of remote amperage and voltage control that
can clear your work space, allowing closer work cells, added productivity,
and less clutter.
We see a
lot of shops still relying on older wire feeders, mostly because
they don't know this technology exists and can greatly improve their
productivity and weld quality. By simply upgrading your wire feeder,
you can turn an older power source into a more productive welding
unit.
Q: Why should
I upgrade my wire feeder and when?
A: Wire feeders
are designed to push wire. If they're not pushing wire, it's time to
change to a newer model. It's time to upgrade when weld quality begins
to deteriorate and you begin to have other performance issues (feeding,
for example). That's the simple answer.
In reality,
the evolution of wire feeding technology over the past few years has
been such that a feeder implemented today can drastically outperform
a feeder you purchased five years ago. Newer models allow for a greater
number of programs to be stored and to be regulated within a matter
of ±0 to 10 volts or 0 to 150 in./min. The enhancement of preflow/postflow
conditions (the shielding gas dispersed before and after a welding sequence)
ensures a stronger weld and drastically reduces instances of crater
cracking. Remote control capabilities, locks, connection systems, and
simplified menus greatly improve productivity, weld quality, and consistency.
New options make many older models obsolete.
If you are in
a situation where you run one wire every day, all day, upgrading is
not as critical. If you're comfortable with that feeder and don't need
it to be more flexible, by all means continue to use what works - there's
no need to complicate proven practices by adding features beyond your
required functions.
Q: How do
I combat "dirty power" (the voltage fluctuations that hamper my arc
stability and weld quality)?
A: Whether it
be other workers running tools and equipment off of the same primary
power line, brownouts, power spikes, or generators that don't regulate
auxiliary power voltage, voltage fluctuations can cause havoc with welding
parameters.
New technologies
are ensuring that operators never experience a fluctuation in the welding
arc. Line voltage compensation devices have been implemented on units
to help curtail such fluctuations. Manufacturers are also creating new
technology that makes sure the primary power remains within certain
parameters. One of the newest multiprocess units available promises
no arc fluctuation or wandering as long as the primary power remains
within a 185 to 635-V range. That covers a "low line" 208-V primary
all the way through a "high line" 575-V primary. This system takes primary
power and converts it to a buss voltage, then using that buss voltage
to drive the control part of the inverter mechanism.
This technology
is ideal for job sites where many workers run tools off of the same
power and where line transients cause voltage fluctuations.
Q: Why am
I being told my current engine drive may not be sufficient for flux
cored welding on structural steel?
A: In the past,
engine-driven welding generators with a constant current (CC) output
have dominated the rental and construction markets. Many contractors
outfit these engine drives with a voltage-sensing wire feeder to enable
flux cored welding. If you're looking to buy a new engine drive, save
the future headache and go straight for an engine drive that also features
constant voltage (CV).
Many engineering
firms, construction companies, and building codes no longer allow flux
cored welding with a CC power source. It does not provide adequate assurance
the weld is being made with the proper voltage. For this reason, CV
power sources are being required, especially for nickel-alloy flux cored
wires used for structural welds on buildings and bridges. Some of the
self-shielded wires are particularly voltage sensitive. A wide variety
of multiprocess machines are available that feature both CC and CV capabilities.
Q: Why do
I care about circuit boards in my engine drive?
A: Because they
can be a giant hassle when not protected. The reality of all work areas
is that they're dirty. Between dirt, dust, humidity, and other intrusive
elements of construction work, there are many things that can cause
circuit board failure. While you'll find some constant current (CC)
machines that completely eliminate circuit boards, you can't escape
them entirely.
Constant voltage
(CV) engine drives require at least one circuit board to control the
arc and are necessary for many flux cored and gas metal arc welding
(GMAW) jobs. Many new engine-drive models are implementing a single
circuit board and encasing it in a "vault" of sorts. Since this practice
has been implemented, circuit boards with that added protection have
had a 99.71% durability rating, which is important because repairing
circuit boards can cost upward of $1,000. Tip one would be to look for
a machine with the fewest amount of circuit boards that still offers
the welding processes you require. Since you can't entirely get rid
of them, it's equally as important to find an engine drive that protects
its circuit boards.
Q: I have
a dependable GMAW unit and need to weld aluminum. Can I do that or should
I look into other options?
A: The aluminum
material thicknesses that can be welded with the GMAW process are 14
gauge and heavier. How heavy depends on the output capacity of the welding
machine being used. To GMA weld aluminum thinner than 14 gauge (0.074
in.), either specialized pulsed gas metal arc or AC gas tungsten arc
welding equipment may be necessary.
Q: What is
the most dependable method for welding aluminum with a GMAW machine?
A: Spray transfer
is the desired mode of metal transfer for welding aluminum. Spray transfer
offers a smooth transfer of molten metal droplets from the end of the
electrode to the molten pool. The droplets crossing the arc are smaller
in diameter than the electrode. There is no short circuiting. The deposition
rate and efficiency are relatively high and the arc is smooth, stable,
and stiff. The weld bead has a nice appearance and a good wash into
the sides. In spray transfer mode, a large amount of heat is involved,
which creates a large weld pool with good penetration that can be difficult
to control and cannot be used on materials thinner than 14 gauge. This
transfer will produce a hissing sound and no spatter.
Q: I'm getting
a lot of melt- through. What am I doing wrong?
A: There are
a number of remedies for this, one of which might be switching to the
gas tungsten arc welding (GTAW) process.
You're getting
the melt-through due to excessive heating of the base material. This
can be dealt with by increasing the travel speed and making shorter
welds. Moving the arc around on the part and spreading the heat will
also help. Eliminating and reducing any gaps will also prove effective,
but you may have to consider switching to a thicker material or going
with an AC GTAW or pulsed GMAW machine.
Rich DePue
has more than 21 years' experience in the welding industry beginning
with 11 years as a welder specialist at West Valley Nuclear Services.
He is currently a Weld Inspection/NDE Manager for Industrial Training
Consultants, Wellsville, N.Y. He is an AWS Certified Welding Inspector
(CWI) and Certified Welding Educator and a New York State Department
of Education Certified Welding Instructor. He also holds ASNT NDE Level
III certification.
Q: In taking
the AWS CWI exam, is it easier to use API 1104 or AWS D1.1 for the code
portion of the exam?
A: Many people
feel API 1104 is easier to use than D1.1 because it is a much smaller
document. I will agree it may be easier to answer questions from a 70-page
code than a 500-page code; however, the AWS CWI exam has a D1.1 flavor
throughout the exam aside from the code portion. Many exam candidates
choosing API 1104 as the code of choice do poorly because they did not
prepare themselves for Part B, which resembles D1.1.
While the CWI
candidate should be generally familiar with all major codes, the advantage
to using D1.1 as the code of choice on the exam is that little or no
attention would have to be paid to 1104 or any other code. Whereas in
using 1104, the candidate must be familiar with 1104 and with several
of the charts and footnotes found in D1.1.
Regardless of
the choice of the code used, to be successful the prospective CWI must
be familiar with AWS D1.1. In my opinion, the best way to prepare for
the CWI exam is to take the week long AWS CWI seminar with the D1.1
Code Clinic.
Q: How can
I obtain welder certification?
A: In general,
a welder can get certified in three ways.
1) Company certification. A welder can get certified to his or her company's
procedures. Welding Procedure Specifications (WPSs) can be developed
by a company in accordance with the requirements of codes, standards,
or in-house contract requirements. With the development and qualification
of a WPS, an individual can be administered a test that will qualify
his or her welding skills.
2) National certification by exam. A welder can enroll in a school or
attend an institution that is an approved or certified testing facility.
At this facility, a test will be administered and the welder's skills
evaluated and certified.
3) National, state, or municipal certification. Welder certification
can be obtained by the issuance of a test by a national-, state-, or
municipal-affiliated entity. A state department of transportation, utility,
or public works can issue certification to national, building, or municipal
codes. The military also offers certification to its codes and standards.
To summarize,
to be certified means, in the eye of a qualified entity, an individual
has met the requirements of a recognized code or standard. There is
also up-to-date, written documentation to represent this activity.
Q: How concerned
should I be about the long-term risk of illness caused by welding fumes?
A: It is best
to treat all welding smoke and fume as potentially harmful and utilize
the best possible techniques and equipment to reduce exposure. Because
of the melting of base and filler metal, the fumes from welding contain
solid particles that can cause temporary dizziness, eye irritation,
nausea, and fever. Fumes can be more serious with the welding of alloy
metals such as stainless steel, manganese, and zinc, and exposure to
these fumes should be kept to a minimum.
Many of the
gases used in welding such as argon, helium, and carbon dioxide are
nontoxic; however, their release during welding displaces oxygen. This
displacement, especially in confined and poorly ventilated areas, can
cause dizziness, unconsciousness, and death.
The long-term
risk of health conditions because of welding has to be taken seriously.
Any injurious conditions encountered will be the result of a lifetime
of exposure to smoke and fumes without adequate air filtration or ventilation.
Therefore, a welder must be cognizant of air quality every working day.
Some tips to reduce exposure to fumes include keeping your head out
of the fume plume, getting as close to the source of fume as possible
with ventilation or making sure there is adequate air movement throughout
the room, and properly cleaning metals prior to welding.
Q: What is
a PQR?
A: PQR is an
abbreviation for Procedure Qualification Record. A PQR is a document
that represents the qualification of a welding procedure. Three ways
a Welding Procedure Specification (WPS) can be qualified include
1) Utilizing a prequalified welding procedure. Some AWS codes offer
prequalified welding procedure specification data to be used for the
development of a welding procedure specification that does not require
testing.
2) Qualify a welding procedure by testing. Welding codes and standards
usually have a specific chapter or section that addresses welding procedure
qualification testing. Testing can include tensile, guided bend, radiography,
ultrasonic, impact, or any combination of these.
3) Utilize noncode company procedural qualification testing. When acceptable
in contract documents, a procedure can be qualified by unconventional
means as required by individual company requirements providing that
good engineering judgment is not compromised. Testing should be compatible
with product design and intended service.
Regardless of
the type of testing used to qualify a procedure, the development of
a WPS and PQR should always be performed by qualified personnel such
as a welding engineer or CWI.
Q: What causes
porosity during welding?
A: In any welding
process, porosity can be caused by the presence of contaminants or moisture
in the welding zone, which includes the base metal, filler metal, shielding
gas, and the surrounding atmosphere. Contaminants can include oil, dirt,
grease, or cutting fluids. Concurrently, moisture can collect in the
flux, shielding gas, or on the base metal, or come from the atmosphere.
Porosity occurring
in a welding process that utilizes an external shielding gas can occur
from using too much or too little gas flow, poor gas quality, or a defective
welding torch, gun, or hose.
Operator technique
can also cause porosity. Electrode, torch, or gun angle can lead to
porosity, as can excessive arc length, electrode extension, or travel
speeds.
Q: How can
I obtain NDE certification?
A: The certification
of personnel performing nondestructive inspection can be accomplished
by the following methods:
1) Obtain certification through training and testing by the American
Society of Nondestructive Testing (ASNT). Providing the candidate has
the required experience and training, ASNT has exams for all levels
and all NDE methods. An inspector can participate in NDE training and
testing at several schools and institutions nationwide in order to obtain
ASNT certification as an NDE trainee or levels I, II, or III.
2) Utilize the requirements of ASNT-SNT-TC-1A. A company can certify
its own personnel using the requirements set forth in the Recommended
Practice SNT-TC-1A. These requirements include the proper number of
training hours, experience hours, and written and practical testing.
Such training and testing should be performed by a Level III or duly
designated company party or approved third party.