|
Welding
Data
Inspection and Welding
Repairs of Pressure Vessels
BY
S. V. GUPTE
B.E., D.M.E.
ASNT LEVEL III - RT,MT,PT,VT
PRESSURE VESSEL INSPECTOR (API 510), (CCOE)
PAINT AND COATING INSPECTOR (NACE - INDIA)
LEAD AUDITOR QMS
ABSTRACTS
Repairs are required
for pressure vessels in order to restore its original / intended operating
condition, safe operation and to prolong trouble free service life.
The vessel condition deteriorate due to various factors mainly Mechanical
Problems, Process Related Problems and Corrosion Problems. Repairs are
required to be planned and carried out under the strict supervision
and control of a competent Inspector.
The paper briefs the
various steps involved in:
- Decision making for
the repairs depending on location and nature of defect within the pressure
vessel as per ASME as well as API 510 code.
- Welding procedure qualifications.
- Materials and Welding
consumables to be used for procedure qualification.
- Requirements and limitations
of controlled deposition welding as an alternative to PWHT, or where
Impact testing is a requirement.
- By using preheating
methods where Impact testing is not a requirement.
- Method of "Temper
bead techniques".
- Method of "Half
bead technique".
- NDT that can be employed
before, during and after welding.
- Necessity of PWHT and
Hydrostatic tests.
- Repairs and precautions
during overlay weld repairs.
- Methods and precautions
to be taken during alterations and re-rating of pressure vessels.
- Aspects of reporting
and re-inspection.
The Paper aims to brief
the interested audience involved in welding inspection and repairs of
pressure vessels that can be conducted in Shut downs within Chemical,
Refinery, Petrochemicals and Fertilizer industries; various methods
of weld repairs and related activities such as testing after welding.
Key Words:
| Owner user |
: |
Owner or a user
organization of the equipment. |
| Repairer |
: |
The agency or organization,
appointed by the owner user for repairs of the equipment. |
| Inspector |
: |
A competent inspection
engineer having full knowledge of the pressure vessel construction,
in-service inspection welding etc. |
| Designer |
: |
A competent Pressure
Vessel Design Engineer. |
| Code |
: |
Code or standard
used for design / construction and Inspection of Pressure vessel. |
| NDT inspector |
: |
A competent NDT
inspector having thorough knowledge and experience of NDT techniques
involved in Construction and repairs. |
| PWHT |
: |
Post Weld Heat Treatment
given to the Pressure vessel during construction or repairs. |
1.0 Introduction:
Repair and maintenance of parts and components is a major activity in
any process industry. Repair welding can be carried out as a logical
procedure that ensures the part is usable and safe. If repairs are done
with proper care or precautions, it can avoid premature failures, large
warranty claims, safety of property and personnel and result in satisfied
customers. Failures of pressure vessels are still observed, which result
in a costly down time of production and product losses also sometimes
it results in environmental hazards and unsafe working conditions or
disasters. Every owner user wants to extract highest possible safe service
life from equipment.
The pressure vessel repairs also cannot be an exception this philosophy.
Modern pressure vessels are constructed in accordance to a recognized
code and established fabrication and welding practice.
2.0
Method of Inspection and decision for repairs.
Pressure vessels are designed to any recognized code of design and construction.
We must under stand that the design thickness can be considerably lower
than the actual Fabricated . During design itself corrosion allowance
is added in the base metal thickness and the manufacturer fabrication
chooses the next available thickness. Thereby we have a excess thickness
available for the service which result in a considerably lower operating
stress value.
Steps involved in
the decision making for repairs.
- Operating conditions,
Inspection history, Material of construction of pressure vessel .
- Reasons for failure
.
- Location of the damaged
area by visual inspection and evaluation by NDTs.
- Re-evaluate the need
for repairs (Back to design calculations).
- Repair Methods, (For
pressure retaining parts) .
- Preparation of repair
procedures.
- Replacement of major
components.
2.1 Operating conditions,
Inspection history, Material of construction of Pressure vessel:
A careful study of the operating parameters and inspection history and
properly maintained internal inspection reports, materials of construction,
its behavior with the process fluid, welding techniques used during
construction, design consideration etc, also gives an adequate confidence
level about the use of pressure vessel. Such information is also useful
for making the repair decision.
Carefully selected material of construction and the fabrication procedures,
welding procedures as well as inspection and certification by the competent
inspection authorities during fabrication stage, always intend to give
such information.
2.2 Reasons for failures:
Undesirable premature failures can occur due to any one or more of the
following reasons . Faulty design, faulty workmanship, wrongly selected
material of construction, wrong welding techniques such premature failures
generally occur in an early service period, where as the normal service
failures are attributed to corrosion, changes in the working parameters,
operation of the vessel for which it is not designed, impurities in
the operating fluids, metallurgical changes in the base metal etc.
Once the damage is identified the pressure vessels must be thoroughly
inspected to evaluate the extent of damage, need for repair and the
repair method.
Thorough visual inspection of the pressure vessel can be supplemented
by a suitable NDT examination, to locate the defects and the extent.
2.3 Location of the damaged
area by visual inspection and evaluation by NDT.
On opening the equipment it is necessary to make it safe for entry as
the remaining fluid or fumes of gases could be dangerous for human life.
The personnel may be required to stay for internal inspection there
could be possible repairs where hot work is involved, there fore a safe
entry permit from a competent authority i.e from the safety and operation
departments.
During internal inspection, some responsible operator should always
be accessible to the inspector performing internal inspection. Such
assistance can always be handy for any critical situation.
The external surface should be checked for any corrosion below the insulation,
obvious leakages, structural attachments, connections, foundations,
leak proof tightness of pressure relief valves etc.
The internal surface should be reasonably cleaned so as to visually
verify its condition , condition of threaded connections, Flange connections,
closures, internalsand damage due to corrosion. Different corrosion
problems anticipated are pitting, line corrosion., General uniform corrosion,
grooving, Galvanic corrosion, Fatigue, Creep, temperature, Hydrogen
attack / Embritterment, Stress corrosion cracking, Inter-granular corrosion,
etc.
The identified damage can be supplemented by NDT for the extent, where
by decision for repairs can be taken confidently, various NDT possible,
are UT thickness measurement, UT scanning, RT, MPI and LPT.
2.4 Re-evaluate the need
for repairs (Back to design calculations)
Based on the NDT results obtained, the same can be verified by the designer
and inspector by performing design calculations, to ensure that the
remaining thickness is still safe, and whether the repairs are warranted
or not.
Based on the remaining thickness corrosion rates are calculated and
the MAWP at the available thickness also calculated. If the MAWP required
is lower that the calculated MAWP then the repairs are not warranted
provided the owner user is ready to carry out internal inspection as
per next scheduled interval.
Location of defect is also important. On base metal away from the weld
metal, a monitor thinning can be left unattended. In event there are
borderline case the thickness can be recalculated by carrying our full
RT and thereby revising the Joint efficiency.
Following design considerations
are reviewed during re-evaluation
- Patch repairs welded
by fillet welding can be used on temporary basis. Such repairs shall
be checked and verified by the design Engineer. The same should be replaced
with permanent measure at the next available maintenance opportunity.
A fully encirclement lap joint may be considered as a permanent repair
method. Such full encirclement patches shall also be designed to meet
the code requirements.
- Minimum thickness observed
shall be evaluated for MAWP and the corrosion rate, so as to decide
the next inspection interval.
- Location of localized
corrosion, such as on the base metal, away from L seam, Away from C
seam, on the weld joints, on crown portion of the head, etc. thereby,
comparing the original design requirement. e.g. by carrying out L seam
Radiography, the joint efficiency can be revised to 1 and the remaining
thickness acceptable can be revised.
- The Inspector should
think out all such possibilities and advise the owner user, so as to
take a precise judgment on the repair.
2.5 Repair methods: (For
pressure retaining parts)
- The cracks are gouged
out or removed and weld repairs can be carried out from both sides,
if approach is available,
- The deep pits or localized
corrosion can be weld built to restore the original thickness.
- The larger area, which
cannot be welded by build up, can be replaced with patch or a shell
course or a head.
So far SMAW or GTAW has
been the most widely accepted welding processes in the industry, for
its availability of welding equipment and skilled welders. However FCAW
or GMAW processes can also be used if sufficient expertise and equipment
are available.
Need less to state that any code requirements, contractual requirements
or any statutory / regulatory requirement must be complied during weld
repairs.
Original construction drawing, calculation data and inspection records
are important for repairs. If the original construction data is not
accessible, then an analysis of the base material, including previous
weld deposits, becomes mandatory. If dimensions require close tolerances
or if flatness is critical, then benchmarks that will aid the repair
without causing excessive and expensive damage to the work piece must
be established.
The crack in weld joint or a defect in the base metal can be repaired
by preparing a "U" or a "V" groove to the full depth
and length of crack and then fill up by weld metal deposit as described
here. If the crack exists in the stress concentration region then consult
a competent pressure vessel design Engineer. Corroded area may be restored
by weld metal deposition as described here.
2.6 Preparation of a
repair procedure:
The repair procedure should take care of the requirements of the base
metal, welding consumables, sequential weld deposits, requirements of
preheat, Interpass temperature, post weld heating, PWHT, impact test
and the NDT requirements.
The repair procedure shall be qualified as per the recognized code such
as ASME sec IX, using an experienced welder. Maintain the records of
procedure qualification as well as performance qualification.
If PWHT is required in original construction and it is not practicable
or advisable during repairs, then the Inspector and the Pressure Vessel
Design Engineer shall review the reason for original PWHT of the equipment.
If the Original reason why PWHT was done is due to the service requirements,
then the alternative methods given below may be avoided, Details of
Repair Procedures and consideration are given in 3.0 of this article.
It is allowed by the Repair & Inspection code to avoid the PWHT
as well as Pressure test after repairs.
3.0
Considerations for repair Procedures: [1 , 2]
3.1 Repair procedure alternative to PWHT, Pre
heating method, where impact testing is not done on the original equipment.
- Impact testing is not
required when this welding method is used.
- This procedure is limited
to P1-Gr. 1 & 2; P3 -Gr. 1 & 2 (Excluding Mn-Mo steels)
- The weld area is pre
heated and maintained at a minimum 150 deg C, during welding. The temperature
is measured to ensure 4" material or 4 times thickness ( whichever
is greater) from the each edge of weld is maintained during welding.
- The maximum Interpass
temperature does not exceed 315 deg C
- Carry out welding as
per the qualified procedure.
3.2 Repair procedure
alternative to PWHT, where impact testing is performed on the original
equipment.
When the original construction required impact test, Notch toughness
testing as required by the code of construction is required. A procedure
need to be qualified separately by using a groove welding on the plate
Some additional requirements that can be considered over and above the
supplementary essential variable are:
- This procedure is limited
to P1; P3 and P4 steels.
- All supplementary essential
elements of ASME Section IX para QW-250 are applied.
- The weld area is pre
heated and maintained at a minimum 150 deg C, during welding. The temperature
is measured to ensure 4" material or 4 times thickness (whichever
is greater) from the each edge of weld is maintained during welding.
- The maximum Interpass
temperature does not exceed 315 deg C .
- Maximum heat input shall
be calculated and implemented during repairs. The maximum heat inputs
as per qualified procedure must not exceed during welding.
- Qualification thickness
for the plate material and the grooves are as per the table 1.
- If the welding is to
be done under NACE standard, MR 0175, then additional test for hardness
measure to be applied.
- For SMAW welding process,
electrodes with additional supplemental diffusible hydrogen designator
H8 or lower shall be used. The gas used in GTAW or GMAW or FCAW shall
exhibit a dew point no higher than minus 50 deg C.
- Welding shall be carried
out as per controlled deposition, temper bead or Half bead technique.
- After completion of
welding, without allowing to reduce the preheat, the temperature is
raised to 230 to 280 Deg C. and held for minimum period of about 2 Hrs
to assist as Hydrogen bake out treatment.
- The Hydrogen bake out
treatment can be omitted if electrodes having supplemental diffusible
hydrogen designator H4 are used.
- After cooling the weld
metal, the excess layer of reinforcement is ground off to match the
surface contour of base metal.
3.3 Non-Destructive Examination
and testing of repaired location.
- The prepared surface
can be checked by using MPI or LPT before welding.
- After completion of
welding, NDE acceptable to the Authorized Inspector or the owner user
are selected and applied to ensure soundness of the weld.
- After repairs the need
for pressure test is to be decided by the Inspector. The test temperature
and the minimum design metal temperature of Pressure vessel shall be
carefully evaluated.
- If Hydrostatic test
is impracticable, then pneumatic test should be considered with appropriate
safety consideration.
3.4 Repair to Stainless
steel overlays and clad.
- In event any overlay
or cladding area is removed, then the base metal gets exposed to the
service environment.
- The Inspector should
give consideration to remove the possible entrapped hydrogen if the
service and the base metal is prone to hydrogen entrapment, hydrogen
embrittlement, Temper embrittlement etc. A heating treatment such as
Hydrogen bake out at 230 to 280Deg C, for about 2 Hrs. shall be given.
4.0
Execution of welding repairs:
- The repairer, under
close supervision and surveillance of the Inspector, executes actual
repairs. The written and qualified procedures are strictly followed.
In case the Impact testing is specified, the welding parameters are
also monitored and ensured to be within the range at which the procedure
is qualified.
- Specified NDE before
welding repairs and after welding repairs are carried out and shall
be approved by the Inspector.
- After repairs the inspection
record and the history of equipment, giving details of repairs, is updated
and next inspection schedule shall be recommended to the owner user.
5.0 Welding techniques: [1, 2]
5.1 Temper bead welding
technique:
The heat affected zone of the bottom bead due to the top bead applied
with lower size electrode, leaves less than 20 to 30 % of the weld metal
cross sectional area as a " typical columnar grains" and the
balance is a normalized structure.
The top layer of the reinforcement mainly consisting of columnar grains,
is required to be ground out, to match the surface contour.
5.2 Half bead welding
technique:
After every pass, the top half of the weld bead is ground off before
applying the next layer.
Such half bead technique also achievs the similar effect of temper bead
technique, but then the consumption of welding electrodes can shoot
up.
6.0
Conclusion:
I wish to draw the following conclusions:
- Repairs of pressure
vessels are not always warranted, the decision of welding repairs must
be taken with due consideration to the location of defect, carefully
evaluated and interpreted NDE results, Design Calculations, Construction
condition such as PWHT and Impact test.
- Once the decision of
welding repairs is taken then it is necessary to document the repair
procedure giving details of NDT test necessary, Per heat and PWHT, welding
sequence, monitoring the welding parameters, pressure test requirements
etc.
- Prepare the inspection
reports and follow up inspection at a predefined inspection interval.
7.0
References:
- API 510 - Pressure vessel
inspection code.
- ANSI NB 23 - National
Board Inspection code.
Table 1: Qualification
thicknesses for test coupon and test repair groove.
|
Depth
of
Test Groove
|
Repair
groove Depth
|
Thickness
of
Test Coupon
|
Plate
Thickness of Base
|
|
t
|
<
t
|
<
2"
|
Up
to 2"
|
|
t
|
<
t
|
>
2"
|
Above
2"
|
Santosh Gupte can be
contacted at guptesantosh@hotmail.com
Welding
Data
|